CoreWeave contracted capacity by site
Company: Core Scientific
The claim, verbatim
Contracted high-density colocation capacity totals about 590 MW: Denton about 260 MW, Dalton about 175 MW, Muskogee about 70 MW, Marble about 65 MW and Austin about 20 MW.
Source (primary)
Investor Conference Call Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗
Quote: “Denton, TX Dalton, GA Muskogee, OK Marble, NC Austin, TX Total Delivery Plan Target Denton Marble ~260 MW ~175 MW ~70 MW ~65 MW ~20 MW ~590 MW”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Investor Conference Call Presentation
Quote: “Denton, TX Dalton, GA Muskogee, OK Marble, NC Austin, TX Total Delivery Plan Target Denton Marble ~260 MW ~175 MW ~70 MW ~65 MW ~20 MW ~590 MW”