jain.com

CoreWeave-funded build-out costs

Company: Core Scientific

Subject kind
financing
Statement date
2025-10-30
Promised amount
750000000.0 USD
Current status
stated

The claim, verbatim

CoreWeave funds up to $1.5 million per MW, or about $750 million, of data center build-out costs, credited against hosting payments at no more than 50% of monthly fees until fully repaid.

Source (primary)

Investor Conference Call Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗

Quote: “Up to $1.5 Million per MW (or approximately $750 Million) of data center build out costs are funded by CoreWeave and credited against hosting payments at no more than 50% of monthly fees until fully repaid.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Investor Conference Call Presentation

Quote: “Up to $1.5 Million per MW (or approximately $750 Million) of data center build out costs are funded by CoreWeave and credited against hosting payments at no more than 50% of monthly fees until fully repaid.”

View cached copy (2026-11-06)Live source ↗