Site buildout capex per MW

Company: Core Scientific

Subject kind
guidance
Statement date
2026-07-28
Promised amount
12000000.0 USD/MW
Current status
stated

The claim, verbatim

Core Scientific estimates average site buildout capex of $11 million to $12 million per MW, excluding tenant fit-out costs of $1 million to $2 million per MW.

Source (primary)

Second Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “Estimating $11 million - $12 million / MW as an average capex range for the site buildouts”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Second Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Estimating $11 million - $12 million / MW as an average capex range for the site buildouts”

View cached copy (2026-11-06)Live source ↗Archive.org ↗