CoreWeave contract term
Company: Core Scientific
The claim, verbatim
The CoreWeave contract covers about 590 MW of infrastructure and about 800 MW gross, on a 12-year term with two 5-year options; the Austin contract term is 7 years with elective extensions.
Source (primary)
Third Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “~590MW infrastructure ~800MW gross 12-year contract with two 5-year options”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Third Quarter Fiscal Year 2026 Earnings Presentation
Quote: “~590MW infrastructure ~800MW gross 12-year contract with two 5-year options”