Promised amount
600.0 MW
Current status
stated

The claim, verbatim

About 600 MW of additional grid capacity under the AMD reservation is progressing through load study review at Pecos, Texas and Muskogee, Oklahoma.

Source (primary)

core-scientific 8-K exhibit (q3fy26earningsdeckvfinal.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-06)Live source ↗

Quote: “POWER UNDER LOAD STUDY ~600 MW Additional grid capacity progressing through load study review”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (q3fy26earningsdeckvfinal.htm)

Quote: “POWER UNDER LOAD STUDY ~600 MW Additional grid capacity progressing through load study review”