Full AMD-related 530 MW delivery

Company: Core Scientific

Subject kind
facility timeline
Statement date
2026-11-04
Promised by
2028-12-31
Promised amount
530.0 MW
Current status
stated

The claim, verbatim

The full 530 MW of AMD-related leased capacity is to be delivered by the end of 2028.

Source (primary)

core-scientific 8-K exhibit (q3fy26earningsdeckvfinal.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-06)Live source ↗

Quote: “With the full 530 MW delivered by the end of 2028”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (q3fy26earningsdeckvfinal.htm)

Quote: “With the full 530 MW delivered by the end of 2028”

View cached copy (2026-11-06)Live source ↗