Corsicana funding split per megawatt
Company: Riot - Project: Corsicana
The claim, verbatim
The funding structure assigns $2 million per MW to site preparation and electrical infrastructure, and $4 million per MW to reimbursing the tenant after each phase enters service and starts paying rent.
Source (primary)
Riot Platforms Bitcoin Sales Fuel Data-Center Expansion - The Cryptonomist (-, news_article)
View cached copy (2026-11-05)Live source ↗Archive.org ↗
Quote: “Another $4 million per megawatt will reimburse the tenant after each phase enters service and starts paying rent.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot Platforms Bitcoin Sales Fuel Data-Center Expansion - The Cryptonomist
Quote: “Another $4 million per megawatt will reimburse the tenant after each phase enters service and starts paying rent.”