jain.com

Corsicana lease capacity of 910 MW

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2026-11-04
Promised amount
910.0 MW
Current status
stated

The claim, verbatim

The Corsicana lease covers 910 MW of critical IT capacity and carries approximately $1.8 billion in average annual rent, including escalators.

Source (primary)

Riot Platforms Tops Revenue Estimates, Signs $28 Billion AI Lease for Corsicana Campus - Yahoo Finance (-, news_article)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “The agreement covers 910 megawatts of critical IT capacity and carries approximately $1.8 billion in average annual rent, including escalators.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot Platforms Tops Revenue Estimates, Signs $28 Billion AI Lease for Corsicana Campus - Yahoo Finance

Quote: “The agreement covers 910 megawatts of critical IT capacity and carries approximately $1.8 billion in average annual rent, including escalators.”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

confirms Riot Platforms Jumps 13% After Signing $28 Billion AI Data Center Lease With Anthropic - bloomingbit

Quote: “Riot signed a 15-year lease covering 910 megawatts of power capacity at its Corsicana, Texas, facility”

View cached copy (2026-11-05)Live source ↗

confirms Riot Platforms Stock Jumps 14% on $28 Billion AI Lease at Texas Site - BigGo Finance

Quote: “covers 910 megawatts of critical IT capacity”

View cached copy (2026-11-05)Live source ↗