2024 target: 16 MW HPC critical IT load
Company: Core Scientific
What the later record shows
Delivered on time
The merger proxy says the 16 MW Austin facility had commenced operations before June 3, 2024, which is within the 2024 target. A later deck also lists delivery of the 16 MW to CoreWeave ahead of schedule, though the exact date is unclear.
“March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”
2025-05-07 · First Quarter Fiscal Year 2025 Earnings Presentation View cached copy (2026-10-16)Live source ↗Archive.org ↗
“Following the commencement of operations in the Austin, Texas facility, on June 3, 2024, Core Scientific entered into a series of long-term contracts”
2025-09-25 · Core Scientific DEFM14A filed 2025-09-26 View cached copy (2026-08-31)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The company's 2024 target is 16 MW of HPC critical IT load.
Source (primary)
core-scientific 8-K exhibit (corescientificq32024earn.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “2024 goals and targets MW HPC critical IT load 16”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificq32024earn.htm)
Quote: “2024 goals and targets MW HPC critical IT load 16”
confirms Core Scientific DEFM14A filed 2025-09-26
Quote: “Following the commencement of operations in the Austin, Texas facility, on June 3, 2024, Core Scientific entered into a series of long-term contracts”
confirms First Quarter Fiscal Year 2025 Earnings Presentation
Quote: “March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”