West Texas 1,400MW site substation energization April 2026

Company: IREN

This claim was marked delayed on October 24, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-11-25
Promised by
2026-04-30
Promised amount
1400.0 MW
Current status
delayed

What the later record shows

The date slipped · new target June 30, 2026

The West Texas 1,400MW site is Sweetwater 1, which has the same $11.7 million connection deposits. The November 2025 10-Q loosened the April 2026 target to Q2 calendar 2026, and no passage confirms energization.

“As of March 31, 2025 we had paid $11.7 million of connection deposits to connect Sweetwater 1 directly to the Electricity Reliability Council of Texas (“ERCOT”) grid.”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
“we are targeting grid connection and a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗

Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN is targeting an April 2026 substation energization date for its 1,400MW West Texas development site.

Source (primary)

iren 8-K exhibit (irisenergylimited-exx994se.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗

Quote: “we have announced a new 1,400MW data center development site located in the renewables-heavy West region of Texas, USA. As of September 30, 2024 we have paid $11.7 million of connection deposits and are targeting a April 2026 substation energization date”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irisenergylimited-exx994se.htm)

Quote: “we have announced a new 1,400MW data center development site located in the renewables-heavy West region of Texas, USA. As of September 30, 2024 we have paid $11.7 million of connection deposits and are targeting a April 2026 substation energization date”

View cached copy (2026-10-24)Live source ↗

delays IREN 10-Q filed 2025-11-06

Quote: “we are targeting grid connection and a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1”

View cached copy (2026-08-31)Live source ↗

delays iren 8-K exhibit (irenlimited-exx994mar2025.htm)

Quote: “As of March 31, 2025 we had paid $11.7 million of connection deposits to connect Sweetwater 1 directly to the Electricity Reliability Council of Texas (“ERCOT”) grid.”

View cached copy (2026-10-15)Live source ↗

Record of changes

October 24, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 24, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.