Sweetwater 1 energization
Company: IREN
What the later record shows
Outcome not yet confirmed
Through November 2025 Sweetwater 1 energization remained a target for April 2026 / Q2 2026. Nothing after the due date confirms or denies it.
“Sweetwater Hub (2GW) • Sweetwater 1 (1,400MW) substation energization targeting April 2026”
2025-11-05 · iren 8-K exhibit (q1fy26resultspressreleas.htm) View cached copy (2026-09-27)Live source ↗
“we are targeting grid connection and a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗
Checked October 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Sweetwater 1 (1.4GW) is on track for energization in April 2026.
Source (primary)
iren 8-K exhibit (q2fy25resultspresentatio.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-20)Live source ↗
Quote: “Sweetwater 1 on-track for April 2026 energization Sweetwater 1 (1.4GW)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (q2fy25resultspresentatio.htm)
Quote: “Sweetwater 1 on-track for April 2026 energization Sweetwater 1 (1.4GW)”
confirms iren 8-K exhibit (q2fy25resultspressreleas.htm)
Quote: “Sweetwater 1 energization on-track for April 2026 (1.4GW)”