West Texas 1,400MW site substation energization April 2026
Company: IREN
What the later record shows
The date slipped · new target June 30, 2026
P19 ties the 1,400MW West Texas site to Sweetwater 1. Its energization target was later restated from April 2026 to Q2 calendar 2026, and no passage confirms energization.
“We are targeting a substation energization date of April 2026 and late 2027 for Sweetwater 1 and Sweetwater 2, respectively.”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
“a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1 and the fourth quarter of calendar year 2027 for Sweetwater 2”
2026-02-04 · IREN 10-Q filed 2026-02-05 View cached copy (2026-08-31)Live source ↗
Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN is developing a 1,400MW data center site in West Texas and is targeting substation energization in April 2026.
Source (primary)
iren 8-K exhibit (irenlimited-exx992sep2024x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗
Quote: “are targeting a April 2026 substation energization date”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenlimited-exx992sep2024x.htm)
Quote: “are targeting a April 2026 substation energization date”
delays IREN 10-Q filed 2026-02-05
Quote: “a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1 and the fourth quarter of calendar year 2027 for Sweetwater 2”
delays iren 8-K exhibit (irenlimited-exx994mar2025.htm)
Quote: “We are targeting a substation energization date of April 2026 and late 2027 for Sweetwater 1 and Sweetwater 2, respectively.”