West Texas 1,400MW site substation energization April 2026

Company: IREN

This claim was marked delayed on October 18, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-03-19
Promised by
2026-04-30
Promised amount
1400.0 MW
Current status
delayed

What the later record shows

The date slipped · new target June 30, 2026

P19 ties the 1,400MW West Texas site to Sweetwater 1. Its energization target was later restated from April 2026 to Q2 calendar 2026, and no passage confirms energization.

“We are targeting a substation energization date of April 2026 and late 2027 for Sweetwater 1 and Sweetwater 2, respectively.”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
“a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1 and the fourth quarter of calendar year 2027 for Sweetwater 2”
2026-02-04 · IREN 10-Q filed 2026-02-05 View cached copy (2026-08-31)Live source ↗

Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN is developing a 1,400MW data center site in West Texas and is targeting substation energization in April 2026.

Source (primary)

iren 8-K exhibit (irenlimited-exx992sep2024x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗

Quote: “are targeting a April 2026 substation energization date”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irenlimited-exx992sep2024x.htm)

Quote: “are targeting a April 2026 substation energization date”

View cached copy (2026-10-18)Live source ↗

delays IREN 10-Q filed 2026-02-05

Quote: “a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1 and the fourth quarter of calendar year 2027 for Sweetwater 2”

View cached copy (2026-08-31)Live source ↗

delays iren 8-K exhibit (irenlimited-exx994mar2025.htm)

Quote: “We are targeting a substation energization date of April 2026 and late 2027 for Sweetwater 1 and Sweetwater 2, respectively.”

View cached copy (2026-10-15)Live source ↗

Record of changes

October 18, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 18, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 18, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.