Sweetwater substation energization April 2026
Company: IREN
What the later record shows
The date slipped · new target June 30, 2026
The Sweetwater substation energization target moved from April 2026 to 'the second quarter of calendar year 2026' in the 10-K and later 10-Qs. No passage reports that energization happened.
“we are targeting grid connection and a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗
“a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1 and the fourth quarter of calendar year 2027 for Sweetwater 2”
2026-02-04 · IREN 10-Q filed 2026-02-05 View cached copy (2026-08-31)Live source ↗
Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN is targeting an April 2026 substation energization date for the Sweetwater project.
Source (primary)
iren 8-K exhibit (irenlimited-exx992dec2024x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗
Quote: “We are targeting an April 2026 substation energization date.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenlimited-exx992dec2024x.htm)
Quote: “We are targeting an April 2026 substation energization date.”
delays IREN 10-Q filed 2025-11-06
Quote: “we are targeting grid connection and a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1”
delays IREN 10-Q filed 2026-02-05
Quote: “a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1 and the fourth quarter of calendar year 2027 for Sweetwater 2”