Total miners operated and energized hash rate, March 2025

Company: Core Scientific

Subject kind
facility capacity
Statement date
2025-04-06
Promised amount
163000.0 units
Current status
stated

The claim, verbatim

As of March 2025 month-end, Core Scientific operated approximately 163,000 bitcoin miners in its data centers for self-mining and hosting, with a total energized hash rate of 19.1 EH/s.

Source (primary)

core-scientific 8-K exhibit (march25productionreportfin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-17)Live source ↗

Quote: “As of month-end, the Company operated approximately 163,000 bitcoin miners in our data centers for both self-mining and hosting, representing a total energized hash rate of 19.1 EH/s.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (march25productionreportfin.htm)

Quote: “As of month-end, the Company operated approximately 163,000 bitcoin miners in our data centers for both self-mining and hosting, representing a total energized hash rate of 19.1 EH/s.”

View cached copy (2026-10-17)Live source ↗