jain.com

ERCOT load classification at Hunt and Pecos

Company: Core Scientific

Subject kind
regulatory
Statement date
2026-10-14
Promised amount
731.0 MW
Current status
stated

The claim, verbatim

ERCOT conditionally classified 431 MW at Hunt and 300 MW at Pecos as base load, with another 300 MW at Pecos as studied load.

Source (primary)

KBW keeps Core Scientific at outperform, says AMD’s 1.9 GW reservation is overlooked - Yahoo Finance (-, news_article)
View cached copy (2026-10-16)Live source ↗

Quote: “ERCOT had conditionally classified 431 MW at Hunt and 300 MW at Pecos as base load, with another 300 MW at Pecos as studied load.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms KBW keeps Core Scientific at outperform, says AMD’s 1.9 GW reservation is overlooked - Yahoo Finance

Quote: “ERCOT had conditionally classified 431 MW at Hunt and 300 MW at Pecos as base load, with another 300 MW at Pecos as studied load.”

View cached copy (2026-10-16)Live source ↗