300 MW remaining HPC capacity
Company: Core Scientific
The claim, verbatim
After the CoreWeave allocation, Core Scientific still has about 300 MW available for HPC hosting for other clients or CoreWeave, plus about 120 MW of support infrastructure.
Source (primary)
Core Scientific, Inc. Investor and Analyst Event June 12, 2024 Transcript (IR page (investors.corescientific.com), earnings_call)
View cached copy (2026-10-16)Live source ↗Archive.org ↗
Quote: “after allocating the 200 megawatts for CoreWeave, we still have another 300 megawatts to offer for HPC hosting”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
Sullivan said the reallocation leaves about 300 MW for GPUs to host other clients or CoreWeave, plus another 120 MW needed to support those facilities.
Confirmed in the source:
- After allocating 200 MW to CoreWeave, Core Scientific has about 300 MW left for HPC hosting
- The remaining 300 MW could go to other clients or to CoreWeave
- About 120 MW of additional infrastructure is needed to support those facilities
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11128/pdf/June_2024_Investor_Day_Transcript_061224.pdf) in full (94,603 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Core Scientific, Inc. Investor and Analyst Event June 12, 2024 Transcript
Quote: “after allocating the 200 megawatts for CoreWeave, we still have another 300 megawatts to offer for HPC hosting”