CoreWeave 200 MW operational in H1 2025
Company: Core Scientific
What the later record shows
The date slipped · new target December 31, 2025
By late October 2025 only ~120+ MW was reported energized, short of the 200 MW expected to be operational in H1 2025. The company then pointed to 250 MW by end of 2025.
“~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
“On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-10-16)Live source ↗Archive.org ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core Scientific expects the 200 MW of CoreWeave HPC hosting infrastructure to reach operational status in the first half of 2025.
Source (primary)
Core Scientific, Inc. Investor and Analyst Event June 12, 2024 Transcript (IR page (investors.corescientific.com), earnings_call)
View cached copy (2026-10-16)Live source ↗Archive.org ↗
Quote: “we expect to achieve operational status in the first half of 2025”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The CEO, CFO and COO each said the 200 MW for CoreWeave would be operational in the first half of 2025.
Confirmed in the source:
- Core Scientific expects the 200 MW of CoreWeave HPC hosting infrastructure to reach operational status in the first half of 2025
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11128/pdf/June_2024_Investor_Day_Transcript_061224.pdf) in full (94,603 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Core Scientific, Inc. Investor and Analyst Event June 12, 2024 Transcript
Quote: “we expect to achieve operational status in the first half of 2025”
delays core-scientific 8-K exhibit (ef20057996_ex99-1.htm)
Quote: “~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress”
delays Investor Conference Call Presentation
Quote: “On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”