2024 operational HPC infrastructure target
Company: Core Scientific
What the later record shows
Delivered on time · happened March 31, 2024
The 16 MW of Austin HPC capacity was delivered to CoreWeave in March 2024, within the 2024 target year.
“March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”
2025-05-06 · core-scientific 8-K exhibit (exhibit992-q12025earning.htm) View cached copy (2026-10-16)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
2024 target of 16 MW operational HPC infrastructure
Source (primary)
Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗
Quote: “MW operational HPC infrastructure ... 16”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The 2024 goals and targets table pairs the MW operational HPC infrastructure row with a value of 16.
Confirmed in the source:
- Core Scientific's 2024 goals include 16 MW of operational HPC infrastructure
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11129/pdf/Core_Scientific_Q2_2024_Earnings_Presentation.pdf) in full (24,266 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “MW operational HPC infrastructure ... 16”
confirms core-scientific 8-K exhibit (exhibit992-q12025earning.htm)
Quote: “March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”