Contract remaining 118 MW for HPC
Company: Core Scientific
What the later record shows
Delivered on time
The December 3, 2024 presentation lists the remaining 118 MW as 'Contracted', so this was done before the 2024 year-end deadline. The exact date is not given.
“Contracted remaining 118 MW of infrastructure available for HPC hosting Executed on pipeline of opportunities to increase our infrastructure capacity”
2024-12-03 · December 2024 Convertible Note Presentation View cached copy (2026-09-01)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
2024 catalyst: contract remaining 118 MW of infrastructure available for HPC hosting
Source (primary)
Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗
Quote: “Contract remaining 118 MW of infrastructure available for HPC hosting”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The 2024 catalysts slide lists this as the first item.
Confirmed in the source:
- A 2024 catalyst is contracting the remaining 118 MW of infrastructure available for HPC hosting
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11129/pdf/Core_Scientific_Q2_2024_Earnings_Presentation.pdf) in full (24,266 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “Contract remaining 118 MW of infrastructure available for HPC hosting”
confirms December 2024 Convertible Note Presentation
Quote: “Contracted remaining 118 MW of infrastructure available for HPC hosting Executed on pipeline of opportunities to increase our infrastructure capacity”