Full 382 MW HPC delivery by H1 2026
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
No passage reports cumulative delivered HPC capacity reaching 382 MW by H1 2026. The later passages are forecasts or contract descriptions only.
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
382 MW of HPC ASDC infrastructure (deliveries of 80, 40, 80, 70 and 112 MW) estimated to be delivered from H2 2024 through H1 2026
Source (primary)
Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗
Quote: “382 MW HPC application-specific data center (ASDC) infrastructure estimated delivery timeline H2 2024 H1 2025 H2 2025 H1 2026”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The delivery timeline slide shows these five deliveries, which sum to 382 MW, across H2 2024 to H1 2026.
Confirmed in the source:
- 382 MW of HPC application-specific data center infrastructure is planned
- Planned deliveries are 80, 40, 80, 70 and 112 MW
- The estimated delivery timeline runs from H2 2024 through H1 2026
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11129/pdf/Core_Scientific_Q2_2024_Earnings_Presentation.pdf) in full (24,266 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “382 MW HPC application-specific data center (ASDC) infrastructure estimated delivery timeline H2 2024 H1 2025 H2 2025 H1 2026”