2024 target: 16 MW HPC critical IT load
Company: Core Scientific
What the later record shows
Delivered on time · happened March 31, 2024
The Q1 2025 materials say the 16 MW of billable capacity at Austin was delivered to CoreWeave in March 2024. That is within the 2024 target year.
“March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”
2025-05-06 · core-scientific 8-K exhibit (exhibit992-q12025earning.htm) View cached copy (2026-10-16)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
2024 goal of 16 MW HPC critical IT load.
Source (primary)
Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗
Quote: “2024 goals and targets MW HPC critical IT load 16”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The '2024 goals and targets' slide lists 16 for 'MW HPC critical IT load'.
Confirmed in the source:
- Core Scientific's 2024 goals and targets list 16 MW of HPC critical IT load.
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Third Quarter Fiscal Year 2024 Earnings Presentation
Quote: “2024 goals and targets MW HPC critical IT load 16”
confirms core-scientific 8-K exhibit (exhibit992-q12025earning.htm)
Quote: “March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”