Additional power at existing and new sites
Company: Core Scientific
The claim, verbatim
Approximately 300 MW of additional power available at existing sites and 400 MW of potential additional power at new sites.
Source (primary)
Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗
Quote: “~300 MW of additional power available at existing sites 400 MW of potential additional power available at new sites”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The data center growth slide lists ~300 MW of additional power at existing sites and 400 MW of potential additional power at new sites.
Confirmed in the source:
- About 300 MW of additional power is available at existing sites
- 400 MW of potential additional power is available at new sites
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Third Quarter Fiscal Year 2024 Earnings Presentation
Quote: “~300 MW of additional power available at existing sites 400 MW of potential additional power available at new sites”