CoreWeave delivery: 500 MW by 2H 2026

Company: Core Scientific

Subject kind
facility timeline
Statement date
2024-11-06
Promised by
2026-12-31
Promised amount
500.0 MW
Current status
stated

The claim, verbatim

Cumulative HPC infrastructure delivery to CoreWeave of 500 MW in 2H 2026; approximately 500 MW contracted to CoreWeave for delivery 2025-2026.

Source (primary)

Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗

Quote: “Approximately 500 MW contracted to CoreWeave for delivery 2025 - 2026”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The presentation states approximately 500 MW contracted to CoreWeave for delivery 2025-2026, and its timeline shows 500 MW cumulative in 2H 2026.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Third Quarter Fiscal Year 2024 Earnings Presentation

Quote: “Approximately 500 MW contracted to CoreWeave for delivery 2025 - 2026”

View cached copy (2026-10-16)Live source ↗