CoreWeave delivery: 382 MW by 1H 2026
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
Later decks restate the plan as 250 MW by end-2025 and ~590 MW by early 2027. No passage reports how many MW were actually delivered by 1H 2026.
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cumulative HPC infrastructure delivery to CoreWeave of 382 MW in 1H 2026.
Source (primary)
Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗
Quote: “Cumulative infrastructure delivery timeline 200MW 270MW 382MW 500MW 1H 2025 2H 2025 1H 2026 2H 2026”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The cumulative delivery timeline on the CoreWeave transaction summary slide shows 382 MW in 1H 2026.
Confirmed in the source:
- Cumulative HPC infrastructure delivery to CoreWeave is scheduled at 382 MW in 1H 2026
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Third Quarter Fiscal Year 2024 Earnings Presentation
Quote: “Cumulative infrastructure delivery timeline 200MW 270MW 382MW 500MW 1H 2025 2H 2025 1H 2026 2H 2026”