CoreWeave delivery: 200 MW by 1H 2025
Company: Core Scientific
What the later record shows
The date slipped · new target December 31, 2025
As of late October 2025, only ~120+ MW was reported energized at Denton and Marble, well short of 200 MW. The company's timeline then targeted 250 MW cumulative by end of 2025.
“~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
“On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cumulative HPC infrastructure delivery to CoreWeave of 200 MW in 1H 2025.
Source (primary)
Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗
Quote: “Cumulative infrastructure delivery timeline 200MW 270MW 382MW 500MW 1H 2025 2H 2025 1H 2026 2H 2026”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The cumulative delivery timeline on the CoreWeave transaction summary slide shows 200 MW in 1H 2025.
Confirmed in the source:
- Cumulative HPC infrastructure delivery to CoreWeave is scheduled at 200 MW in 1H 2025
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Third Quarter Fiscal Year 2024 Earnings Presentation
Quote: “Cumulative infrastructure delivery timeline 200MW 270MW 382MW 500MW 1H 2025 2H 2025 1H 2026 2H 2026”
delays core-scientific 8-K exhibit (ef20057996_ex99-1.htm)
Quote: “~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress”