CoreWeave funds ~$750M of build-out costs

Company: Core Scientific

Subject kind
financing
Statement date
2025-05-07
Promised amount
750000000.0 USD
Current status
stated

The claim, verbatim

Up to $1.5 million per MW (approximately $750 million) of data center build-out costs are funded by CoreWeave and credited against hosting payments at no more than 50% of monthly fees until repaid.

Source (primary)

First Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗

Quote: “Up to $1.5 Million per MW (or approximately $750 Million) of data center build out costs are funded by CoreWeave and credited against hosting payments at no more than 50% of monthly fees until fully repaid”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The transaction summary footnote states these funding and credit terms.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11247/pdf/First+Quarter+Fiscal+Year+2025+Earnings+Presentation.pdf) in full (28,649 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms First Quarter Fiscal Year 2025 Earnings Presentation

Quote: “Up to $1.5 Million per MW (or approximately $750 Million) of data center build out costs are funded by CoreWeave and credited against hosting payments at no more than 50% of monthly fees until fully repaid”