Company-funded capex for 70 MW CoreWeave expansion

Company: Core Scientific

Subject kind
financing
Statement date
2026-05-06
Promised amount
104000000.0 USD
Current status
stated

The claim, verbatim

For the additional 70 MW expansion, Core Scientific is responsible for funding $104M of capex ($1.5M per MW) for the powered core and shell, with no capex credit.

Source (primary)

First Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗

Quote: “For the additional 70 MW expansion, Core Scientific is responsible for funding $104 Million of capex ($1.5M per MW) for the powered core and shell”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

A contract summary footnote states the company funds $104 million of powered core and shell capex for the 70 MW expansion with no capex credit.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11271/pdf/Q1+FY26+earnings+deck.pdf) in full (14,811 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms First Quarter Fiscal Year 2026 Earnings Presentation

Quote: “For the additional 70 MW expansion, Core Scientific is responsible for funding $104 Million of capex ($1.5M per MW) for the powered core and shell”

View cached copy (2026-10-16)Live source ↗Archive.org ↗