250 MW CoreWeave delivery by end of 2025

Company: Core Scientific

Subject kind
facility timeline
Statement date
2025-05-06
Promised by
2025-12-31
Promised amount
250.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

The passages restate the ~590 MW CoreWeave contract and per-site billable power figures. None reports cumulative billable capacity delivered by end of 2025.

Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Core Scientific says it is on track to deliver 250 MW of billable colocation capacity by the end of 2025.

Source (primary)

core-scientific 8-K exhibit (exhibit992-q12025earning.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗

Quote: “On track to deliver 250 MW by the end of 2025”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The delivery-plan slide on billable colocation capacity states the company is on track to deliver 250 MW by the end of 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000162828025023161/exhibit992-q12025earning.htm) in full (28,145 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (exhibit992-q12025earning.htm)

Quote: “On track to deliver 250 MW by the end of 2025”

View cached copy (2026-10-16)Live source ↗

Record of changes

October 16, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 16, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.