jain.com

~420 MW active power across 33 data centers

Company: CoreWeave

Subject kind
facility capacity
Statement date
2025-05-18
Promised amount
420.0 MW
Current status
stated

The claim, verbatim

As of March 31, 2025, CoreWeave had about 420 MW of active power across 33 data centers, up from about 360 MW across 32 data centers at December 31, 2024.

Source (primary)

coreweave 8-K exhibit (d19327dex992.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗

Quote: “Mar-25 33 data centers ~420 MW active power”

How we checked this

Checked on October 16, 2026. The cited source supports every part of this claim.

The footprint slide lists both figures with matching as-of dates in its notes.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1769628/000119312525122115/d19327dex992.htm) in full (13,593 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms coreweave 8-K exhibit (d19327dex992.htm)

Quote: “Mar-25 33 data centers ~420 MW active power”

View cached copy (2026-10-15)Live source ↗