Total contracted power ~4.2 GW

Company: CoreWeave

Subject kind
facility capacity
Statement date
2026-10-09
Promised amount
4200.0 MW
Current status
stated

The claim, verbatim

CoreWeave's total contracted power reached roughly 4.2 GW as of August 11, up from about 3.7 GW at the end of Q2.

Source (primary)

CoreWeave Lands Higher-Priced AI Compute Deals – And Seeks $3B More To Fund Expansion - Stocktwits (-, news_article)
View cached copy (2026-10-11)Live source ↗Archive.org ↗

Quote: “The firm said total contracted power reached roughly 4.2 gigawatts (GW) as of August 11, up from about 3.7 GW at the end of the second quarter (Q2).”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The article reports contracted power of roughly 4.2 GW as of August 11, up from about 3.7 GW at the end of Q2.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://stocktwits.com/news-articles/markets/equity/core-weave-lands-higher-priced-ai-compute-deals-seeks-3-b-more/cZtrFqjRB5H) in full (6,699 characters, retrieved October 11, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CoreWeave Lands Higher-Priced AI Compute Deals – And Seeks $3B More To Fund Expansion - Stocktwits

Quote: “The firm said total contracted power reached roughly 4.2 gigawatts (GW) as of August 11, up from about 3.7 GW at the end of the second quarter (Q2).”

View cached copy (2026-10-11)Live source ↗Archive.org ↗