Sweetwater 2 energization late 2027
Company: IREN - Project: Sweetwater 2
The claim, verbatim
Sweetwater 2 (600MW) is targeting energization in late 2027; fiber loop design to Sweetwater 1 is complete and procurement of long-lead high voltage equipment is underway.
Source (primary)
iren 8-K exhibit (ef20051646_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-11)Live source ↗
Quote: “Targeting energization late 2027”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
IREN's June 2025 monthly update lists Sweetwater 2 at 600MW and says it is targeting energization in late 2027. The same section says fiber loop design to Sweetwater 1 is complete and long-lead high voltage equipment procurement is underway.
Confirmed in the source:
- Sweetwater 2 has 600MW of capacity
- Sweetwater 2 is targeting energization in late 2027
- Design work is complete for a direct fiber loop connecting Sweetwater 1 and Sweetwater 2
- Procurement of long-lead high voltage equipment for Sweetwater 2 is underway
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036125024971/ef20051646_ex99-1.htm) in full (23,104 characters, retrieved October 11, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ef20051646_ex99-1.htm)
Quote: “Targeting energization late 2027”