Sandersville project fully funded via $2.276B senior secured notes

Company: CleanSpark - Project: Sandersville

Subject kind
financing
Statement date
2026-10-09
Promised amount
2276000000.0 USD
Current status
stated

The claim, verbatim

CleanSpark said its Sandersville, Georgia data center project is fully funded through completion following the September closing of $2.276 billion in non-dilutive senior secured notes carrying a 7.875% annual interest rate and maturing in 2031.

Source (primary)

CleanSpark Still Has 13K Bitcoin On Its Books, But It's Ending Its Monthly Updates As Data Center Buildout Accelerates - TradingView (-, news_article)
View cached copy (2026-10-10)Live source ↗Archive.org ↗

Quote: “With non-dilutive bond financing now in place, our Sandersville project is fully funded through completion”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The article reports every element of this claim, including the CEO's description of the bonds as non-dilutive financing.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.tradingview.com/news/stocktwits:eca6731ca094b:0-cleanspark-still-has-13k-bitcoin-on-its-books-but-it-s-ending-its-monthly-updates-as-data-center-buildout-accelerates/) in full (6,342 characters, retrieved October 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark Still Has 13K Bitcoin On Its Books, But It's Ending Its Monthly Updates As Data Center Buildout Accelerates - TradingView

Quote: “With non-dilutive bond financing now in place, our Sandersville project is fully funded through completion”

View cached copy (2026-10-10)Live source ↗Archive.org ↗

confirms CleanSpark Still Has 13K Bitcoin On Its Books, But It's Ending Its Monthly Updates As Data Center Buildout Accelerates - Stocktwits

Quote: “With non-dilutive bond financing now in place, our Sandersville project is fully funded through completion”

View cached copy (2026-10-10)Live source ↗Archive.org ↗

confirms CleanSpark Still Has 13K Bitcoin On Its Books, But It's Ending Its Monthly Updates As Data Center Buildout Accelerates - TradingView

Quote: “With non-dilutive bond financing now in place, our Sandersville project is fully funded through completion”

View cached copy (2026-10-12)Live source ↗Archive.org ↗