Mikeska/Milsing/McLennan 500 MW each

Company: Cipher Mining - Project: Reveille Site

Subject kind
facility capacity
Statement date
2025-08-06
Promised amount
1500.0 MW
Current status
stated

The claim, verbatim

Mikeska, Milsing and McLennan each have potential capacity of 500 MW, pending load studies and ERCOT LFL approval; Reveille has 70 MW.

Source (primary)

cipher-mining 8-K exhibit (ciphermining_businessupd.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗

Quote: “Reflects total potential capacity of 500 MW per site – pending load studies and ERCOT LFL approval”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The future-growth slide lists 70 MW for Reveille and 500 MW of potential capacity for each of the other three sites, with a footnote that these depend on load studies and ERCOT LFL approval.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000079/ciphermining_businessupd.htm) in full (19,841 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)

Quote: “Reflects total potential capacity of 500 MW per site – pending load studies and ERCOT LFL approval”