Abernathy JV 84 MW Q4 2026
Company: TeraWulf - Project: Abernathy HPC Campus
The claim, verbatim
Abernathy JV 84 MW (TeraWulf share) scheduled for Q4 2026, with an additional 84 MW Abernathy JV option.
Source (primary)
Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “Abernathy JV (84 MW, Q4)”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The presentation lists Abernathy JV (84 MW, Q4) and a separate Abernathy JV Option (84 MW), with a footnote that Abernathy figures reflect TeraWulf's 50.1% share.
Confirmed in the source:
- Abernathy JV 84 MW is listed with a Q4 timing
- Abernathy JV capacity figures represent TeraWulf's 50.1% joint venture interest
- The 84 MW Abernathy capacity appears in the 2026 column of the development runway chart
- There is an additional 84 MW Abernathy JV option
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23490/pdf/TeraWulf+Q1+2026+Investor+Presentation+%28May+2026%29.pdf) in full (27,753 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Q1 2026 Earnings Update Presentation
Quote: “Abernathy JV (84 MW, Q4)”