Fluidstack JV options 336 MW

Company: TeraWulf - Project: Abernathy HPC Campus

Subject kind
partnership
Statement date
2025-11-10
Promised by
2028-12-31
Promised amount
336.0 MW
Current status
stated

The claim, verbatim

Exclusive Fluidstack JV options for 336 MW: Abernathy Phase II 168 MW in 2027-2028 and a new site (TBD) of 168 MW.

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “Exclusive Fluidstack JV Options – 336 MW • 2027-2028: Abernathy Phase II -- 168 MW • New Site: TBD – 168 MW”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The capacity overview lists exclusive Fluidstack JV options of 336 MW: Abernathy Phase II of 168 MW in 2027-2028 and a new site, still to be determined, of 168 MW.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23306/pdf/WULF_Q3_2025_Investor_Update_%28Nov_2025%29vF.pdf) in full (31,442 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “Exclusive Fluidstack JV Options – 336 MW • 2027-2028: Abernathy Phase II -- 168 MW • New Site: TBD – 168 MW”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-11-10.