Gross MW online by YE2025
Company: WhiteFiber
What the later record shows
Partly delivered
A June 2026 investor deck reports about 11 MW online in 2025 (MTL-1 plus MTL-3, operational November 2025), against the ~16 MW target. MTL-2 (5 MW) was still shown with capacity and customer TBD.
“The facility has been retrofitted to Tier-3 standards and was completed and operational in November 2025.”
2026-03-25 · WhiteFiber 10-K filed 2026-03-26 View cached copy (2026-08-31)Live source ↗
“MTL-1 4.0 MW MTL-3 7.0 MW NC-1(5) 99.0 MW Footprint Pipeline(3) MTL-2 5.0 MW(2) ~11 MW Online in 2025”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
“MTL-2 5 Gross MW Capacity: TBD Customer: TBD IT Load: 3 MW Average Term: TBD”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
WhiteFiber expects approximately 16 gross MW of data center capacity online by year-end 2025.
Source (primary)
whitefiber 8-K exhibit (ea025484401ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-05)Live source ↗
Quote: “MW Online by YE 2025E ~16”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The 'At a Glance' slide lists '~16' MW online by YE 2025E and notes that all MW figures are gross.
Confirmed in the source:
- WhiteFiber expects about 16 MW of data center capacity online by year-end 2025
- The MW figures are stated on a gross basis
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390025081421/ea025484401ex99-1_white.htm) in full (24,103 characters, retrieved October 5, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms whitefiber 8-K exhibit (ea025484401ex99-1_white.htm)
Quote: “MW Online by YE 2025E ~16”