jain.com

Ontario B300 cloud contract commencing November

Company: WhiteFiber

Subject kind
customer
Statement date
2026-09-30
Promised by
2026-11-30
Promised amount
165200000.0 USD
Current status
stated

The claim, verbatim

WhiteFiber is to deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario under a three-year agreement worth $165.2 million, targeted to commence in November 2026.

Source (primary)

WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research (-, news_article)
View cached copy (2026-10-03)Live source ↗Archive.org ↗

Quote: “The company is assigned to deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario. This three-year agreement is targeted to commence in November, representing $165.2 million in contract value.”

How we checked this

Checked on October 5, 2026. The cited source supports part of this claim, but not all of it.

The article confirms the Ontario B300 deployment, three-year term, $165.2 million value and a November start, but does not state the year of that November start.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of the publisher (https://www.zacks.com/stock/news/2998344/wyfi-stock-rallies-56-in-6-months-heres-what-you-should-know) in full (15,036 characters, retrieved October 3, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research

Quote: “The company is assigned to deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario. This three-year agreement is targeted to commence in November, representing $165.2 million in contract value.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗