The claim, verbatim
TeraWulf said it has done substantial additional technical work and is making meaningful changes to the Lake Hawkeye site plan in response to town questions, and asked Lansing to keep the review process open.
Source (primary)
Lansing moves toward data center ban as TeraWulf debate reaches turning point - Fingerlakes1.com (-, news_article)
View cached copy (2026-10-02)Live source ↗
Quote: “We've listened, done substantial additional technical work, and are making meaningful changes to the site plan in response.”
How we checked this
Checked on October 4, 2026. The cited source supports every part of this claim.
The article quotes TeraWulf's vice president of project development saying the company has done additional technical work, is changing the site plan in response to town questions, and wants the review process kept open.
Confirmed in the source:
- TeraWulf, through Pace Rally, its vice president of project development, told the Lansing Town Board it had done substantial additional technical work
- TeraWulf said it is making meaningful changes to the Lake Hawkeye site plan in response to the town's questions and requests for information
- TeraWulf asked Lansing to keep the existing review process open
What we did: Read our cached copy of the publisher (https://www.fingerlakes1.com/2026/10/02/lansing-moves-toward-data-center-ban-as-terawulf-debate-reaches-turning-point/) in full (18,681 characters, retrieved October 2, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Lansing moves toward data center ban as TeraWulf debate reaches turning point - Fingerlakes1.com
Quote: “We've listened, done substantial additional technical work, and are making meaningful changes to the site plan in response.”