~1.41 GW of contracted leases across five campuses
Company: Applied Digital
The claim, verbatim
As of May 31, Applied Digital had executed long-term leases for about 1,410 MW of contracted critical IT load across five campuses.
Source (primary)
Billionaire Investor Takes a Stake in Applied Digital (APLD) - TradingView (-, news_article)
View cached copy (2026-10-01)Live source ↗Archive.org ↗
Quote: “As of May 31, the company has executed long-term leases representing approximately 1,410 MW of contracted critical IT load across five campuses.”
How we checked this
Checked on October 3, 2026. The cited source supports every part of this claim.
The article states that as of May 31 the company had executed long-term leases for about 1,410 MW of contracted critical IT load across five campuses.
Confirmed in the source:
- As of May 31, Applied Digital had executed long-term leases
- The leases represent approximately 1,410 MW of contracted critical IT load
- The contracted load is spread across five campuses
What we did: Read our cached copy of the publisher (https://es.tradingview.com/news/benzinga:ddb7ecce2094b:0-billionaire-investor-takes-a-stake-in-applied-digital-apld/) in full (7,195 characters, retrieved October 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Billionaire Investor Takes a Stake in Applied Digital (APLD) - TradingView
Quote: “As of May 31, the company has executed long-term leases representing approximately 1,410 MW of contracted critical IT load across five campuses.”