Ontario 1,392 B300 GPU three-year contract
Company: WhiteFiber
The claim, verbatim
WhiteFiber will deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario under a three-year agreement worth $165.2 million, targeted to commence in November 2026.
Source (primary)
WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - TradingView (-, news_article)
View cached copy (2026-10-01)Live source ↗Archive.org ↗
Quote: “The company is assigned to deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario. This three-year agreement is targeted to commence in November, representing $165.2 million in contract value.”
How we checked this
Checked on October 12, 2026. The cited source supports part of this claim, but not all of it.
The article confirms the GPU count, Ontario third-party data center location, three-year term, $165.2 million value and a November start. It does not state the year of the November start; 2026 is implied by the article's timing but not stated.
Confirmed in the source:
- WhiteFiber is to deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario
- The Ontario GPU deployment is under a three-year agreement
- The Ontario agreement represents $165.2 million in contract value
- The Ontario agreement is targeted to commence in November
We could not confirm this from the cited source:
- The Ontario agreement is targeted to commence in November 2026 specifically (the article says only 'November' and gives no year)
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of the publisher (https://www.tradingview.com/news/zacks:8751f15c7094b:0-wyfi-stock-rallies-56-in-6-months-here-s-what-you-should-know/) in full (6,899 characters, retrieved October 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - TradingView
Quote: “The company is assigned to deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario. This three-year agreement is targeted to commence in November, representing $165.2 million in contract value.”
confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research
Quote: “The company is assigned to deploy 1,392 NVIDIA B300 GPUs at a third-party data center in Ontario. This three-year agreement is targeted to commence in November, representing $165.2 million in contract value.”