jain.com

Three additional HPC campuses totaling 1.4 GW being marketed

Company: Applied Digital

Subject kind
facility capacity
Statement date
2026-09-29
Promised amount
1400.0 MW
Current status
stated

The claim, verbatim

Beyond Ellendale, the Company is actively marketing three additional campuses totaling 1.4 GW.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “continues with three additional campuses we are actively marketing totaling 1.4 GW”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “continues with three additional campuses we are actively marketing totaling 1.4 GW”

View cached copy (2026-09-29)Live source ↗Archive.org ↗