AI Cloud Service full operation by end of 2023
Company: Applied Digital
What the later record shows
The date slipped
In January 2024 the company said network-component delays affected cluster commissioning. In October 2024 the Jamestown HPC facility was still described as nearing completion. Later filings place the cloud business only at third-party colocation sites in Colorado, Minnesota and Utah, not Jamestown.
“While the delay in network components did have a significant impact on the timing of commissioning clusters and on our revenue and EBITDA”
2024-01-16 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to the Company's 106 MW Data center hosting facility.”
2024-10-21 · ARS View cached copy (2026-09-01)Live source ↗Archive.org ↗
“We currently operate our Cloud Services Business in three states: Colorado, Minnesota, and Utah, by renting space at third party colocation centers”
2026-04-07 · Applied Digital 10-Q filed 2026-04-08 View cached copy (2026-08-30)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The AI Cloud Service is expected to be fully operational by the end of 2023, hosted at the 9MW Jamestown HPC facility and third-party colocation facilities.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “The service is expected to be fully operational by the end of 2023 and will be hosted at the standalone 9MW HPC facility in Jamestown”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release says the service is expected to be fully operational by the end of 2023 and will be hosted at the 9MW Jamestown HPC facility along with third-party colocation facilities.
Confirmed in the source:
- The AI Cloud Service is expected to be fully operational by the end of 2023
- The service will be hosted at the standalone 9MW HPC facility in Jamestown
- The service will also be hosted at third-party colocation facilities
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/66/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (23,127 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The service is expected to be fully operational by the end of 2023 and will be hosted at the standalone 9MW HPC facility in Jamestown”
confirms Earnings Release
Quote: “The service is expected to be fully operational by the end of 2023 and will be hosted at the standalone 9MW HPC facility in Jamestown”
confirms Earnings Release
Quote: “The service is expected to be fully operational by the end of 2023 and will be hosted at the standalone 9MW HPC facility in Jamestown along with third-party colocation facilities”
confirms Earnings Release
Quote: “The service is expected to be fully operational by the end of 2023 and will be hosted at the standalone 9MW HPC facility in Jamestown”
delays Earnings Release
Quote: “While the delay in network components did have a significant impact on the timing of commissioning clusters and on our revenue and EBITDA”
delays ARS
Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to the Company's 106 MW Data center hosting facility.”
delays Applied Digital 10-Q filed 2026-04-08
Quote: “We currently operate our Cloud Services Business in three states: Colorado, Minnesota, and Utah, by renting space at third party colocation centers”