Nearly 500MW hosting capacity by early 2023

Company: Applied Digital

Subject kind
facility capacity
Statement date
2022-10-11
Promised by
2023-03-31
Promised amount
500.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

Ellendale (180MW) began energizing March 4, 2023, and Jamestown runs at about 106MW. The September 2025 report lists only these two sites, about 286MW in total, with Garden City absent, so roughly 286 of the nearly 500MW was delivered.

“The site is currently expected to energize before the end of February.”
2023-01-09 · Earnings Release View cached copy (2026-10-23)Live source ↗Archive.org ↗
“The Company took possession of the land on August 15, 2022, built a hosting facility, and began energizing the site on March 4, 2023.”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
“We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW as follows”
2025-09-20 · ARS View cached copy (2026-09-01)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company is building to nearly 500MW of hosting capacity across three sites by early calendar 2023, all already contracted.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “building to nearly 500MW of hosting capacity by early calendar 2023, all of which is already contracted”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The CEO describes progressing three datacenter sites toward nearly 500MW by early calendar 2023, all already contracted.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/42/applied-blockchain-reports-fiscal-first-quarter-2023/) in full (25,723 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “building to nearly 500MW of hosting capacity by early calendar 2023, all of which is already contracted”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “building to nearly 500MW of hosting capacity by early calendar 2023, all of which is already contracted”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “building to nearly 500MW of hosting capacity by early calendar 2023, all of which is already contracted”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “building to nearly 500MW of hosting capacity by early calendar 2023, all of which is already contracted”

View cached copy (2026-10-08)Live source ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2022-10-11.