jain.com

Portfolio ~1.4 GW critical IT across five campuses

Company: Applied Digital

Subject kind
facility capacity
Statement date
2026-09-24
Promised amount
1400.0 MW
Current status
stated

The claim, verbatim

Contracted AI infrastructure portfolio spans five campuses totaling about 1.4 GW of critical IT load.

Source (primary)

Applied Digital Alabama Data Center Is Confirmed, but Brookwood Still Has Questions - remio (-, news_article)
View cached copy (2026-09-28)Live source ↗Archive.org ↗

Quote: “The project expands Applied Digital’s contracted AI infrastructure portfolio to five campuses. Together, those projects represent about 1.4 gigawatts of critical IT load.”

How we checked this

Checked on September 30, 2026. The cited source supports every part of this claim.

The article states that the portfolio now covers five campuses representing about 1.4 gigawatts of critical IT load.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.remio.ai/post/applied-digital-alabama-data-center-is-confirmed-but-brookwood-still-has-questio) in full (26,155 characters, retrieved September 28, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital Alabama Data Center Is Confirmed, but Brookwood Still Has Questions - remio

Quote: “The project expands Applied Digital’s contracted AI infrastructure portfolio to five campuses. Together, those projects represent about 1.4 gigawatts of critical IT load.”

View cached copy (2026-09-28)Live source ↗Archive.org ↗