Camp Pendleton $2.4M construction option

Company: CleanSpark - Project: Camp Pendleton

Subject kind
financing
Statement date
2016-12-29
Promised amount
2362472.0 USD
Current status
stated

The claim, verbatim

$2,362,472 construction, integration and commissioning contract option expected to be exercised

Source (primary)

CleanSpark 10-K filed 2016-12-30 (SEC EDGAR, sec_filing)
View cached copy (2026-09-27)Live source ↗

Quote: “that may result in an additional contract option for $2,362,472 for construction, integration and commissioning of the designed and optimized System configuration. We expect the prime contractor to exercise these options.”

How we checked this

Checked on September 29, 2026. The cited source supports every part of this claim.

The 10-K states the option amount and management's expectation that it will be exercised. It also notes the option 'may result' and is not yet guaranteed.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000166357716000436/mainbody.htm) in full (178,833 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2016-12-30

Quote: “that may result in an additional contract option for $2,362,472 for construction, integration and commissioning of the designed and optimized System configuration. We expect the prime contractor to exercise these options.”