The claim, verbatim

CleanSpark operating microgrid project at Marine Corps Base Camp Pendleton School of Infantry

Source (primary)

CleanSpark 10-K filed 2016-12-30 (SEC EDGAR, sec_filing)
View cached copy (2026-09-27)Live source ↗

Quote: “CleanSpark was subcontracted to provided design, development, integration, and installation services for the FractalGrid at the School of Infantry in the 52 Area of Marine Corps Base Camp Pendleton. The Project was subsequently transferred to CleanSpark”

How we checked this

Checked on September 29, 2026. The cited source supports every part of this claim.

The 10-K says the project was transferred to CleanSpark, which assumed operations and supplies power from the microgrid assets to the base.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000166357716000436/mainbody.htm) in full (178,833 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2016-12-30

Quote: “CleanSpark was subcontracted to provided design, development, integration, and installation services for the FractalGrid at the School of Infantry in the 52 Area of Marine Corps Base Camp Pendleton. The Project was subsequently transferred to CleanSpark”