Camp Pendleton construction execution window

Company: CleanSpark - Project: Camp Pendleton

Subject kind
facility timeline
Statement date
2018-01-15
Promised by
2018-10-31
Current status
verified

What the later record shows

Delivered late · happened May 31, 2019, new target March 31, 2019

The January 2019 10-K said the work was still expected to finish in early 2019, so it was not done by October 2018. The May 2019 10-Q says the scope of work was completed in May 2019.

“The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019.”
2019-01-14 · CleanSpark 10-K filed 2019-01-15 View cached copy (2026-09-27)Live source ↗
“The Company began on-site work for this project in February of 2018 and completed its scope of work in May 2019.”
2019-05-14 · CleanSpark 10-Q filed 2019-05-15 View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Expects to execute construction contract between February 2018 and October 2018

Source (primary)

CleanSpark 10-K filed 2018-01-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-27)Live source ↗

Quote: “As of the date of this filing we anticipate the Company will execute on the $900,000 construction contract between February 2018 and October 2018”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The 10-K states the company anticipates executing the $900,000 construction contract between February 2018 and October 2018.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000166357718000019/mainbody.htm) in full (207,635 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2018-01-16

Quote: “As of the date of this filing we anticipate the Company will execute on the $900,000 construction contract between February 2018 and October 2018”

View cached copy (2026-09-27)Live source ↗

confirms CleanSpark 10-Q filed 2019-05-15

Quote: “The Company began on-site work for this project in February of 2018 and completed its scope of work in May 2019.”

View cached copy (2026-09-13)Live source ↗

confirms CleanSpark 10-K filed 2019-01-15

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019.”

View cached copy (2026-09-27)Live source ↗

Record of changes

September 27, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 28, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.