Current operational capacity and facilities

Company: Core Scientific

Subject kind
facility capacity
Statement date
2022-03-29
Promised amount
497.0 MW
Current status
stated

The claim, verbatim

Core Scientific had 457MW of power as of December 31, 2021, and 497MW as of January 31, 2022, operating six fully operational data centers in North Carolina (2), Georgia (2), North Dakota (1), and Kentucky (1)

Source (primary)

Core Scientific 10-K filed 2022-03-30 (SEC EDGAR, sec_filing)
View cached copy (2026-09-27)Live source ↗

Quote: “with approximately 457MW of power as of December 31, 2021, and 497MW as of January 31, 2022... at our six fully operational data centers in North Carolina (2), Georgia (2), North Dakota (1) and Kentucky (1).”

How we checked this

Checked on September 29, 2026. The cited source supports every part of this claim.

The filing gives the approximately 457MW and 497MW power figures and lists the six operational data centers by state.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1839341/000119312522088850/d268076d10k.htm) in full (452,768 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Core Scientific 10-K filed 2022-03-30

Quote: “with approximately 457MW of power as of December 31, 2021, and 497MW as of January 31, 2022... at our six fully operational data centers in North Carolina (2), Georgia (2), North Dakota (1) and Kentucky (1).”