Applied Digital Cloud product
Company: Applied Digital
The claim, verbatim
Launched Applied Digital Cloud, a 9 MW HPC data center service in Jamestown, North Dakota
Source (primary)
applied-digital 8-K exhibit (apld_invxfinalpresentati.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗
Quote: “Launched Cloud Business, Applied Digital Cloud 9 MW HPC Data Center In Jamestown, ND”
How we checked this
Checked on September 29, 2026. The cited source supports part of this claim, but not all of it.
The timeline lists launching Applied Digital Cloud and a 9 MW HPC data center in Jamestown, but it is ambiguous whether these are one offering or two separate milestones.
Confirmed in the source:
- Applied Digital launched a cloud business called Applied Digital Cloud
- Applied Digital has a 9 MW HPC data center in Jamestown, North Dakota
We could not confirm this from the cited source:
- Applied Digital Cloud is itself the 9 MW HPC data center service in Jamestown, North Dakota
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487925000076/apld_invxfinalpresentati.htm) in full (26,833 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (apld_invxfinalpresentati.htm)
Quote: “Launched Cloud Business, Applied Digital Cloud 9 MW HPC Data Center In Jamestown, ND”