Launched Applied Digital Cloud, a 9 MW HPC data center service in Jamestown, North Dakota

Source (primary)

applied-digital 8-K exhibit (apld_invxfinalpresentati.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “Launched Cloud Business, Applied Digital Cloud 9 MW HPC Data Center In Jamestown, ND”

How we checked this

Checked on September 29, 2026. The cited source supports part of this claim, but not all of it.

The timeline lists launching Applied Digital Cloud and a 9 MW HPC data center in Jamestown, but it is ambiguous whether these are one offering or two separate milestones.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487925000076/apld_invxfinalpresentati.htm) in full (26,833 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apld_invxfinalpresentati.htm)

Quote: “Launched Cloud Business, Applied Digital Cloud 9 MW HPC Data Center In Jamestown, ND”

View cached copy (2026-09-27)Live source ↗