jain.com

CoreWeave infrastructure capacity

Company: Core Scientific

Subject kind
facility capacity
Statement date
2025-10-29
Promised amount
590.0 MW
Current status
stated

The claim, verbatim

Approximately 590 MW infrastructure (approximately 800 MW gross) for CoreWeave contracts

Source (primary)

core-scientific 8-K exhibit (ef20057996_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “~590 MW infrastructure (~800 MW gross)”

How we checked this

Checked on September 29, 2026. The cited source supports every part of this claim.

The figure appears on the presentation's CoreWeave contract summary slide.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000114036125039864/ef20057996_ex99-1.htm) in full (11,284 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (ef20057996_ex99-1.htm)

Quote: “~590 MW infrastructure (~800 MW gross)”

View cached copy (2026-09-27)Live source ↗